Baselines, adjustments, and measurement.

Learning Track · Module 4: Energy and carbon · Step 29 of 101

Showing content for Europe. Change the region at the top of the page.

  1. Measure the baseline for some weeks before the change, with burn hours and connected load.
  2. Make the change.
  3. Measure the result with the same meters and method.
  4. Adjust for differences, mainly night length.
Saving = (baseline kWh per burn hour − new kWh per burn hour) × burn hours

IPMVP is the common method worldwide. ISO 50015 also covers measurement and verification. South Asia: In India, BEE provides guidance for M&V in ESCO projects. USA: ASHRAE Guideline 14 is also used.

Note

Without data from before the change, you cannot prove the saving later. Start to record energy now.

Sources

  1. IPMVP Core Concepts (Efficiency Valuation Organization)
  2. ISO 50015 Measurement and verification of energy performance
  3. ASHRAE Guideline 14 Measurement of energy, demand, and water savings