Checks to do before you trust the data.
Learning Track · Module 10: SOPs · Step 85 of 101
- Map it to the correct asset in the register.
- Set location and clock: latitude, longitude, time zone.
- Check readings against a clamp meter. Check each phase is on the correct input.
- Test switching and dimming from the platform. Confirm on site.
- Test one alarm, for example open a breaker.
- Record it: date, person, results.
Note
A reversed current transformer gives negative power or a wrong power factor. It is the most common error after installation.
Sources
- IEC 60364-6 Verification
- Controller maker commissioning instructions
Changes: 30 October 2026: First publication: guides for Europe, the Middle East, South Asia, and the USA; failure library; tender clause library; comparisons; tools; downloads. See the changelog. Found a mistake? Report it.