Checks to do before you trust the data.

Learning Track · Module 10: SOPs · Step 85 of 101

  1. Map it to the correct asset in the register.
  2. Set location and clock: latitude, longitude, time zone.
  3. Check readings against a clamp meter. Check each phase is on the correct input.
  4. Test switching and dimming from the platform. Confirm on site.
  5. Test one alarm, for example open a breaker.
  6. Record it: date, person, results.

Note

A reversed current transformer gives negative power or a wrong power factor. It is the most common error after installation.

Sources

  1. IEC 60364-6 Verification
  2. Controller maker commissioning instructions

Changes: 30 October 2026: First publication: guides for Europe, the Middle East, South Asia, and the USA; failure library; tender clause library; comparisons; tools; downloads. See the changelog. Found a mistake? Report it.