The life of a job, from report to close.

Learning Track · Module 8: Maintenance · Step 61 of 101

States: Open, Assigned, In progress, On hold, Resolved, and Closed. A technician resolves the job and records the fix. A supervisor closes it.

Due time = time raised + SLA
Critical 4 h · High 24 h · Normal 48 h · Low 72 h
  • Use Critical only for danger: exposed live parts, a fallen pole, a high-voltage alarm.
  • Put a job on hold only for a real reason. Write the reason.
  • Always record the cause and the part used.
  • Keep one open job per pole.

EN 13306 defines maintenance terms such as corrective and preventive maintenance. It is a useful common language in any region.

Note

In OpenSLMS, every job has a priority and an SLA due time, and late jobs are flagged. See work orders with SLA due times.

Sources

  1. EN 13306 Maintenance terminology
  2. EN 15341 Maintenance key performance indicators
  3. ISO 55000 Asset management: overview, principles and terminology

Changes: 30 October 2026: First publication: guides for Europe, the Middle East, South Asia, and the USA; failure library; tender clause library; comparisons; tools; downloads. See the changelog. Found a mistake? Report it.